Project Description
MEP Contractor | FEMCO & YUKSEL Consortium |
Location | Al Ahsa, KSA |
End User | Ministry of Higher Education |
Client | King Faisal University |
Project Management | University PM |
Consultant | Zuhair Fayez Partnership (ZFP) |
Type of Project | District Cooling & Infrastructure |
Total Value (SAR) | 600.95 Million Saudi Riyal |
Start Date | Aug, 2007 |
Finish Date | Dec, 2011 |
Total Land Area | |
Total Built-up Area |
Work Description
Civil, Mechanical, & Electrical Infrastructure Works for Four (4) Sub – Packages as detailed below
Scope of Work
- Excavation & Backfilling: 428,000 m³ & 1,028,000 m³
- Concrete Works: 50,000 m³
- Asphalt Works: 325,000 m²
- Chilled Water Piping System: 14,800 m
- Sweet Water Piping System: 9,000 m
- Sewage Water Piping System: 10,000 m
- Storm Water Piping System: 13,500 m
- Raw Water Piping System: 12,000 m
- Reverse Osmosis (RO) Unit Capacity 3,500 m³/day
- Sewage Treatment Plant Capacity 3,770 m³/day (2 duty + 1 standby)
- Chiller Plant
- Water Cooled Centrifugal Chillers (Multi Stage): 9 nos. Capacity 3,150 TR each (TOTAL 28,350 TR)
- Evaporator Flow: 3,900 GPM,
- Water Entering Temp. 58°F
- Water Leaving Temp. 38°F”
- Open Circuit Cooling Towers: 8 nos. Capacity 9290 GPM
- Primary Chilled Pumps: 7 nos. TDH 13.7 bar, Capacity 3,877 GPM
- Condenser Water Pumps: 7 nos. TDH 4.5 bar, Capacity 9,290 GPM
- MV Switchgear 13.8 kV
- Generator Plant
- Emergency Generators: 2 nos. Capacity 1,000kVA each
- Diesel Generators: 2 nos. Capacity 1000kW
- Motor Control Centers (MCC)
- Street Lighting
- Panel Boards
- Grounding and Lightning Protection
- Pump Rooms
- SCADA System controlling all campus utility buildings
- BMS System controlling all Colleagues Building