Project Description
Contractor | Faisal Electro-Mechanical Co. Ltd. |
Location | Jeddah, KSA |
End User | Ministry of Higher Education |
Client | King Abdulaziz University |
Project Management | University PM |
Consultant | |
Type of Project | District Cooling & Infrastructure |
Total Value (SAR) | 8.1 Million Saudi Riyal |
Start Date | Nov, 2018 |
Finish Date | Nov, 2020 |
Total Land Area | |
Total Built-up Area |
Work Description
Civil, Electrical & Mechanical works
Scope of Work
- Renovation of Boiler Building Replacement of doors and windows,
- Plastering, painting, ceiling and roof insulation system works.
- Replacement of (3) nos. Diesel type Steam Boiler
- Supply, installation, testing & Commissioning of (2) nos. Electric type Steam Boilers and (1) no. Gas type Steam Boiler with steam capacity 1.5 ton/hr.
- Rehabilitation of (2) nos. Steam Pumps.
- Supply, installation, Testing & Commissioning of AHU & ducting,
- RO Unit, Water Softener Unit, Pumps, pipe & fittings and valves,
- Boiler Plant Fire Fighting System,
- BMS, Main Distribution Board, cable and cable trays.
- Underground existing High Pressure Steam Line Test (X-RAY and REPLICA)