Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Sudair, Riyadh, KSA
End User
Client
Project Management
Consultant
Type of Project
Total Value (SAR) 17.38 Million Saudi Riyal
Start Date Dec, 2022
Finish Date Dec, 2023
Total Land Area
Total Built-up Area

Work Description

Site Work, Civil, Architecture, Structural, Mechanical, Electrical and Landscape Works.

Scope of Work

A – Site Construction

  • Construction of Building for Faculty of Dentistry,
  • Construction Concrete and wall works,
  • Construction finishing works, Hollow metal doors,windows and  frames,
  • Landscape works.

B – Electro-Mechanical Works

  • Air Handing Unit (AHU), Exhaust Fans (EF), HVAC works, Fire Fighting works ,
  • Power outlet works , Transformer , Ring Main Unit (RMU), Motor Control Center (MCC)
  • MDB, Data and Telephone System, IP CCTV System,
  • Low Voltage & Medium Voltage Cables works and BMS System,
  • Conveying system elevators (4 pcs), Freight Elevator (1 pcs)
  • Total Area of Building and Landscaping: Faculty land on around 7100 m2 with 15.000 m2 construction area.