Infrastructure for KFU Teaching Hospital Project in Al-Ahsa, Phase-1

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Al Ahsa, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant Zuhair Fayez Partnership (ZFP)
Type of Project District Cooling & Infrastructure
Total Value (SAR) 290.8 Million Saudi Riyal
Start Date Jun, 2010
Finish Date Jun, 2013
Total Land Area 500,000 m2
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure & Utilities Works

Scope of Work

Site Development

    • Excavation & Backfilling: 263,000 m³ & 220,000 m³
    • Concrete Works: 8,000 m³
    • Asphalt Works: 52,000 m²
    • Curbstone: 10,000 m²
    • Chilled Water Piping System:           4,500 m
    • Storm Water Piping System: 800 m
    • Sewage Water Piping System: 2,200 m
    • Potable Water Piping System: 2,200 m
    • Raw Water Piping System: 2,800 m
    • Well Water Piping System: 500 m for 3 nos. deep well
    • Reverse Osmosis (RO) Unit: 2 nos. Capacity 750 m³/day
    • Break Water Tank: 1 nos. Capacity 500 m³

Chiller Plant

    • Water Cooled Centrifugal Chillers: 6 nos. Capacity 2,151 TR each (TOTAL 12,906 TR)
    • Air Cooler Radiators: 44 nos. Capacity 269 TR each (TOTAL 11,836 TR)
    • Primary Chilled Pumps: 8 nos. TDH 2.6 bar, Capacity 3,250 GPM
    • Condenser Water Pumps: 8 nos. TDH 3.7 bar, Capacity 7,300 GPM
    • Secondary Chilled Pumps: 5 nos. TDH 6 bar, Capacity 5,700 GPM
    • Boilers: 4 nos. Capacity 7,710 kg/hr

Generator Plant

    • Generators: 5 nos. Capacity 2500kVA each
    • MV Switchgear: 1 no. 13.8 kV, 2500 kVA

Pump Rooms

    • Raw Water Pump: 4 nos. TDH 9.5 bar, Capacity 161 GPM
    • Irrigation Water Pump: 3 nos. TDH 6.5 bar, Capacity 250 GPM
    • Fire Pump: 2 nos. TDH 13.5 bar, Capacity 47 GPM

Pipeline Coating Rehabilitation

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Jubail, KSA
End User Saline Water Conversion Corporation (SWCC)
Client Saline Water Conversion Corporation (SWCC)
Project Management SWCC-PM
Consultant
Type of Project Water & Power
Total Value (SAR) 44 Million Saudi Riyal
Start Date Jul, 2009
Finish Date May, 2010
Total Land Area
Total Built-up Area

Work Description

Carbo steel 60″ pipeline A & B STOPAQ (visco elastic coating) coating Works (13km)

Scope of Work

  • Excavation
  • Removal of existing polyethylene coating
  • Surface preparation (sandblasting of existing pipes)
  • Application of new protective coating (Visco elastic coating)
  • “Holiday” insulations testing
  • Backfilling / compacting / restoration of berm
  • Replacement of fence, post for vent valves etc.
  • Fabrication / installation of reinforced concrete culvert pipes
  • Sand stabilization

Jeddah RO III (DHI / JedRO / SA / MSE / OOI) (240 Million Liters Per Day) – Doosan

Project Description

Main Contractor Doosan Heavy Industries & Construction
Sub-Contractor Faisal Electro-Mechanical Co. Ltd.
Location Jeddah, KSA
End User Saline Water Conversation Corp. (SWCC)
Client Saline Water Conversation Corp. (SWCC)
Project Management SWCC-PM
Consultant
Type of Project Water & Power
Total Value (SAR) 57.94 Million Saudi Riyal
Start Date Jul, 2009
Finish Date Sep, 2013
Total Land Area
Total Built-up Area

Work Description

Electrical, Mechanical, & Civil Works for Taprogge Filters

Scope of Work

Progress of Equipment and Piping installation

  • Sea Water Supply Pumps and Screening Equipment
  • Air Compressor System
  • Cartridge Filters
  • Electro Chlorinator Systems
  • Ferric & Polymer Dosing System
  • DMF Back Wash Pumps
  • Filtered Water Pumps
  • Steel Structure (Platform, Pipe Rack, etc.)
  • RO Building: 1st Pass Booster HP Pumps, Turbo Charger, Permeator Pressure Vessels
  • Electrical, Instrumentation & Control system
  • Electrical Equipment: 90 MVA, 380kV GIS and 380/13.8k Transformers
  • 13.8kV and 480V Switchgears, UPS, Rectifiers, 13.8kV/480V Aux.
  • Transformers Cable Trays and bridges.
  • Testing and Commissioning

Preparation of Infrastructure for the University City in Al-Ahsa, Phase-3, Stage-1 (King Faisal University Permanent Campus in Al-Ahsa)

Project Description

MEP Contractor FEMCO & YUKSEL Consortium
Location Al Ahsa, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant Zuhair Fayez Partnership (ZFP)
Type of Project District Cooling & Infrastructure
Total Value (SAR) 600.95 Million Saudi Riyal
Start Date Aug, 2007
Finish Date Dec, 2011
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure Works for Four (4) Sub – Packages as detailed below

Scope of Work

  • Excavation & Backfilling: 428,000 m³ & 1,028,000 m³
  • Concrete Works: 50,000 m³
  • Asphalt Works: 325,000 m²
  • Chilled Water Piping System: 14,800 m
  • Sweet Water Piping System: 9,000 m
  • Sewage Water Piping System: 10,000 m
  • Storm Water Piping System: 13,500 m
  • Raw Water Piping System: 12,000 m
  • Reverse Osmosis (RO) Unit Capacity 3,500 m³/day
  • Sewage Treatment Plant Capacity 3,770 m³/day (2 duty + 1 standby)
  • Chiller Plant
  • Water Cooled Centrifugal Chillers (Multi Stage): 9 nos. Capacity 3,150 TR each (TOTAL 28,350 TR)
  • Evaporator Flow: 3,900 GPM,
  • Water Entering Temp. 58°F
  • Water Leaving Temp. 38°F”
  • Open Circuit Cooling Towers: 8 nos. Capacity 9290 GPM
  • Primary Chilled Pumps: 7 nos. TDH 13.7 bar, Capacity 3,877 GPM
  • Condenser Water Pumps: 7 nos. TDH 4.5 bar, Capacity 9,290 GPM
  • MV Switchgear 13.8 kV
  • Generator Plant
  • Emergency Generators: 2 nos. Capacity 1,000kVA each
  • Diesel Generators: 2 nos. Capacity 1000kW
  • Motor Control Centers (MCC)
  • Street Lighting
  • Panel Boards
  • Grounding and Lightning Protection
  • Pump Rooms
  • SCADA System controlling all campus utility buildings
  • BMS System controlling all Colleagues Building

Preparation of Infrastructure for the University City in Dammam Second Phase (King Faisal University Permanent campus in Dammam)

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 212.84 Million Saudi Riyal
Start Date Jun, 2007
Finish Date Nov, 2009
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure Works

Scope of Work

  • Site Cleaning with Excavation / Filling of 1,230,000 cu.mtr. of Soil.
  • Construction of Roads with 590 Poles of Street Lights, Walkways, & Parking.
  • Installation of Sewer &p; Irrigation Piping, and 34 KM of Water Distribution Network.
  • Setting up of Sewage Treatment Plant of 1,600 cu.mtr. / day capacity and Sewage Pump Lifting station of 50 LPS. capacity.
  • Also Storm Water Pump Station of 250 LPS capacity is constructed.
  • Installation of 4 nos. Chiller Plants of 1,300 Tons capacity and
  • 3 nos. Cooling Towers of 3,900 GPM capacity,
  • Laying of 1.4 KM of Hydronic Pipes, together with Chilled & Condenser Water pumps.
  • Installation of R.O Plant of 400 cu. mtr per day capacity.
  • Facilities like: Telephone & Computer Data System, Clock System,
  • MATV, CCTV Surveillance, CCMS / BMS / Fire Alarm System,
  • Sprinklers, FM 200 Fire Suppression System & Fire Hydrants, are included.
  • Electrical Works include: Installation of 16 KM of U / G conduits for Elect.
  • Cabling.
  • 4 nos. of 1,500 KVA Generators for Emergency Power,
  • 4 nos. Power Transformers, 1 no. MV Switchgear and
  • Installation of 28 KM of 15 KV MV Cables, 2 nos. LV Switchgear,
  • MCCs, Power & Lighting Panels, Lighting Transformers.
  • 10 KM of LV Cables, Control Boards, and Photo-electric Switches for Street Lights.
  • Grounding, Bonding, and Lightning Protection System

Sewage Works Package 5, East side / City Fanar Project

Project Description

MEP Contractor FEMCO & YUKSEL Consortium
Location Dammam, KSA
End User
Client Rikaz Development Company
Project Management
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 11.2 Million Saudi Riyal
Start Date Mar, 2005
Finish Date Aug, 2005
Total Land Area
Total Built-up Area

Work Description

Sewage System consisting of Sewage Network & Lifting Stations

Scope of Work

  • Supply & Installation of uPVC Pipes, diameter ranging from 150 to 400 mm.
  • FRP Pipes from 200 to 800 mm dia. including Valves, Fittings, Inspection Chambers and Manholes.
  • Excavation, De-Watering, Leveling, Back-filling, Compacting and Side Slope Protection.
  • Construction of Lifting Station and Booster Lifting Station which includes
  • Submersible Pumps, Motors, together with Discharge Pipes & Fittings, Check Valve, Gate Valve and Exhaust Ducts.
  • Construction of: Fence, Gates, Walkways, Asphalting,
  • Guard House, Generator Room, and Electrical Room.
  • Architectural Works include Concrete Masonry Units,
  • Elastomeric Membrane Roofing System,
  • Steel Doors & frames, Aluminum Windows,
  • Plastering, Painting, Tiling (interior & exterior) and Toilet Fittings.

Preparation of Infrastructure for the University City in Dammam Phase 4 & 6, Utility Works. (King Faisal University Permanent Campus in Dammam)

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant Saud Consult
Type of Project District Cooling & Infrastructure
Total Value (SAR) 101.39 Million Saudi Riyal
Start Date Mar, 2005
Finish Date Nov, 2007
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure Works

Scope of Work

  • Excavation & Back-filling of 1,362,694 cu. mtr. of Soil,
  • Construction of 107,700 LM of Flexible Pavements
  • 92,200 LM of Curbs & Gutters and 61,000 sq. mtrs. of Sidewalks.
  • 769 LM of Underground Piping (FRP) were laid, and Water Tank of 1,800 cu.mtr. was constructed.
  • R.O Plant of 600 cu.mtr. / day capacity was installed with Water Well and 14.13 KM of Water Network Piping.
  • Sewage Treatment Plant (STP) and Sewage Lift Station is provided with
  • Installation of 5.12 KM of Sanitary Sewage Piping.
  • 5.34 KM of Irrigation Piping has been laid.
  • 50 mtrs. of LPG Pipes (above ground) have been installed with 2 nos. of LPG Tanks of 40,000 USG capacity.
  • 2 nos. of Centrifugal Chillers and 2 nos. of Cooling Towers have also been erected.
  • Electrical Works include: Installation of Power & Distribution Transformers,
  • LV Switchgear, and Street Lighting Poles
  • Communication & Data Processing Equipment, Telephone & Inter-com System.
  • Building Automation & Controls and Security Surveillance System were also added.

Refurbishment Works of Jeddah Phase 4 – Desalination Plant

Project Description

Main Contractor ACWA Power SASAKURA (APS)
Sub-Contractor Faisal Electro-Mechanical Co. Ltd.
Location Jeddah, KSA
End User Saline Water Conversation Corp. (SWCC)
Client Saline Water Conversation Corp. (SWCC)
Project Management SWCC-PM
Consultant
Type of Project Water & Power
Total Value (SAR) 40.5 Million Saudi Riyal
Start Date Sep, 2004
Finish Date Apr, 2007
Total Land Area
Total Built-up Area

Work Description

Rehabilitation Works of Evaporator Tube Bundles and modification of Vacuum System

Scope of Work

  • Removal and Replacement of Brine Pipes, Sea Water Pipes, Water boxes, Demisters & Manhole Covers.
  • Tube Bundles Demolishing & Replacement.
  • Removal and Replacement of: Vent Pipes, Tube Sheets Necks, Tube Support Plates and Intermediate Tube Sheets.
  • Insertion & Expanding of 53,200 nos. of 90/10 Cu.Ni. Tubes (O.D 19 mm x 25000 mm length.) with subsequent
    Leakage Test using Pressure Air.
  • Cleaning, Rust Removal, Sandblasting, & Coating Works.
  • Lining Works ( mounting SS lining material on evaporated internal surface above Demister for Corrosion Protection
    after cleaning )
  • Modification of Evaporator Venting & Vacuum System, Brine Gate Cover and inspection of Brine Heater Tubes.
  • Replacement of Pump Suction & Discharge Valves and Leakage Test.
  • All related Elect. & Instrumentation Works.

Hofuf Water Transmission System

Project Description

Main Contractor Rashid / KSB Fluid System Gmbh
Sub-Contractor Faisal Electro-Mechanical Co. Ltd.
Location Khobar, KSA
End User Saline Water Conversation Corp. (SWCC)
Client Saline Water Conversation Corp. (SWCC)
Project Management SWCC-PM
Consultant
Type of Project Water & Power
Total Value (SAR) 4.6 Million Saudi Riyal
Start Date Dec, 2002
Finish Date June, 2004
Total Land Area
Total Built-up Area

Work Description

Electro – Mechanical Installations and Testing & Commissioning Works

Scope of Work

Mechanical Work:

  • Installation of Pumps.
  • Installation of Surge Vessel and Surge Tank.
  • Installation of SVP Compressor Unit.
  • Fabrication & Installation of Pipes.
  • Installation of Wall Ducts for Drain Stations.
  • Installation of Butterfly Valves, Platform, & Ladder of the Vessel.

Electrical Works:

  • Instrumentation Works in OPS Pump Area.
  • Installation of OPS & EPWTS Interface.
  • SVP instrument Installation, Cabling & Termination
  • Elect. Installation for HOFUF Yard Shafts 2 & 3.

Preparation of Infrastructure for the University City in Dammam Phase 1, Utility Works. (King Faisal University Permanent Campus in Dammam)

Project Description

MEP Contractor FEMCO & YUKSEL Consortium
Location Dammam, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 90.98 Million Saudi Riyal
Start Date Sep, 2002
Finish Date Aug, 2005
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure Works

Scope of Work

  • Development of 77 Hectares area with Excavation / Filling of 774,300 cu.mtr. of soil, preparation of 2.60 KM of Slope Embankment.
  • Construction of Roads with 511 poles of street Lights, Walkways & Parking.
  • Construction of 2.75 KM of Storm Drainage System.
  • Installation of 3.47 KM of Irrigation Piping, and LPG Network of 1.94 KM with
  • Installation of two nos. LPG Tanks with total capacity of 46,000 gallons.
  • Setting-up of R.O. Plant of 600 cu. mtr. per day capacity with Water Well, and with 600 cu. mtr. Underground Water Tank,
  • 600 cu. mtr. Sweet Water Tank and 1800 cu. mtr. Raw Water Tank.
  • Also installed 8.96 KM of Water Distribution Network with pipe sizes ranging from dia.: 25 to 315 mm.
  • Setting-up of Sewage Treatment Plant of 1340 cu .mtr. per day capacity and Installation of 4.62 KM of Sewer Pipelines.
  • Installation of 3 Chiller Plants of 1,300 Tons capacity,
  • 3 nos. Cooling Towers of 3,900 GPM capacity & laying of 6.73 KM of underground Pipes, sizes ranging from 150 to 900 mm. dia.
  • 3 nos. of Chilled & Cond. Water Pumps, 8 nos.of AHUs, & 11 Exhaust Fans were installed.
  • Mech. Works also include packages of Storm Water Pumping Station and Sewer Pumping Station.
  • Construction of ‘Utility Building’ with facilities like: Telephone & Computer Data System, Clock System, MATV, CCTV surveillance,
  • CCMS / BMS / Fire Alarm System incl. Sprinklers, FM 200 Fire Suppression System & Fire Hydrants.
  • Electrical Works include: Installation of 26 KM of uPVC conduits for Elect. Cabling.
  • Emergency Electric Power Sub-station with 2 nos. of 1,500 KVA Generators, Power Transformers,
  • MV Switchgear of MVA / 13.8 MV capacity and Installation of 38.5 KM of 15 KV MV Cables.,
  • LV Switchgear, MCCs, Power & Lighting Panels, Lighting Transformers,
  • 14.7 KM LV Cables, Control Boards, and Photo-electric Switches for Street Lights.
  • Grounding, Bonding, and Lightning Protection System.