P&C Of District Cooling Plant in Community Area

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Jubail, KSA
End User Royal Commission for Jubail and Yanbu
Client Royal Commission for Jubail and Yanbu
Project Management
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 159.73 Million Saudi Riyal
Start Date Jan, 2018
Finish Date Aug, 2020
Total Land Area
Total Built-up Area

Work Description

Civil, Electrical & Mechanical works

Scope of Work

Site Infrastructure Works

  • Storm Water Piping System: 800 m.
  • Potable and Fire Water Piping System: 700 m.
  • Sanitary Water Piping System: 500 m.
  • Break Water Storage Steel Tank: 1 no. 6 m dia. Capacity 150 m³.
  • Potable Water Storage Steel Tank: 1 no. 9 m dia. Capacity 400 m³.
  • Make-Up Water Storage Steel Tanks: 2 nos. 14 m dia. Capacity 2,275 m³.
  • Thermal Energy Storage Steel Tank: 1 no. 23 m dia. Capacity 24,000 ton/hr.

Chiller Plant

  • Electric Operated Overhead Cranes: 2 nos. Lifting Capacity 15 ton.
  • Series Counter Flow Water Cooled Centrifugal Chillers: 6 nos. Capacity 3,000 TR each (TOTAL 18,000 TR).
  • Induced Draft Field Erected Counter Flow Cooling Towers: 3 nos. Capacity 12,400 GPM.
  • Chilled Water Pumps: 3 nos. TDH 3 bar, Capacity 9,000 GPM.
  • Condenser Water Pumps: 3 nos. TDH 4 bar, Capacity 9,000 GPM.
  • MV Switchgears: 2 nos. 4.16 kV and 3 nos. 13.8 kV
  • Diesel Generator: 1 no. 300 kVA

Pump Stations

  • Make-Up Water Pumps: 4 nos. TDH 2 bar, Capacity 376 GPM
  • Fire Pumps: 2 nos. TDH 9 bar, Capacity 750 GPM
  • Submersible Pumps: 2 nos. TDH 3.5 bar, Capacity 1,200 GPM
  • Excavation and Backfilling
  • Expansion Tanks
  • Basket Strainers
  • Firefighting FM200 Clean Agent System
  • Air Handling Units, Package Units, Fan Coil Units and Exhaust Fans
  • Chemical Treatment System
  • Access Control System & SCADA
  • Area Lightning System
  • Telecommunication System

Infrastructure & Electro-Mechanical Works for Wadi Al Hada Residential Compound

Project Description

MEP Contractor SASEL & FEMCO CONSORTIUM
Location Riyadh, KSA
End User Wadi Hanifah Real Est. Development
Client Wadi Hanifah Real Est. Development
Project Management Leman PM
Consultant SaudConsult
Type of Project Residential Compound
Total Value (SAR) 236 Million Saudi Riyal
Start Date May, 2019
Finish Date Feb, 2020
Total Land Area 250,000 m2
Total Built-up Area 150,000 m2

Work Description

Electrical & Mechanical works

Scope of Work

  • Residential compound of 549 units to be built on total land of around: 215,000 m2 with total build up area of around 150,000 m2 works as bellow:
  • Infrastructure work, Electrical and Mechanical works for Residential compound 549 units consisting of: 8no’s Villas 5 bedrooms duplex, 66no’s of 3 bed rooms duplex townhouse, 57no’s of 4 bedrooms triplex townhouse and 338 apartments distributed on 43 buildings. all these to be built on total land of around 215,000 m2 with total build up area of around 150,000 m2.
  • Work includes supply and install the following:
  • 4no’s of chillers 426kw/each
  • Pipes for chilled water, potable water, and firefighting network with required valves
  • Pipes and manholes for sewage system
  • Medium voltage cables network, low voltage cables network
  • 13no’s Oil Type Transformers
  • 5no’s RMU
  • Generators
  • MCC Panels
  • Fuel Tanks
  • BMS

Infrastructure for KFU Teaching Hospital Project in Al-Ahsa, Phase-2

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Al Ahsa, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management KFU-PM
Consultant Al-Saif Consultants
Type of Project District Cooling & Infrastructure
Total Value (SAR) 245.21 Million Saudi Riyal
Start Date Mar, 2015
Finish Date June, 2021
Total Land Area 1,000,000 m2
Total Built-up Area

Work Description

Civil, Electrical & Mechanical works

Scope of Work

Site Infrastructure

  • Excavation: 250,000 m³
  • Backfilling: 450,000 m³
  • Concrete Works: 10,000 m³
  • Precast Fence Wall: 3,000 m
  • Asphalt: 150,000 m²
  • Chilled Water Piping System: 1,000 m
  • Steam and Condensate Water Piping System: 2,000 m
  • Sewerage Piping System: 4,500 m
  • Potable Water Piping System: 5,000 m
  • Raw Water Piping System: 5,000 m
  • Fire Water Piping System: 4,000 m
  • Storm Water Piping System: 2,000 m
  • Irrigation Water Piping System: 6,000 m
  • Deep Well: 4 nos. 250 m
  • Deep Well Water Piping System: 1,000 m
  • Manholes: 110 nos. FRP
  • Water Steel Storage Tanks: 6 nos. Capacities 3,000 m³ each
  • LV, MV and Communication Ductbank: 13,000 m
  • Cabling: 33,000 m
  • Transformers and Substations: 26 nos up to 2,000 kVA
  • External Area Lightning: 950 nos.
  • Reverse Osmosis (RO) Plant: 750 m³/day

Generator Plant

  • Diesel Generators: 11 nos. 2,500 kVA
  • Underground Diesel Tanks: 3 nos. Capacity 40,000 Gallon

Chiller Plant 

  • Water Cooled Centrifugal Chiller: 2 nos. Capacity 2,151 TR each (TOTAL 4,302 TR)
  • Air Cooler Radiators: 16 nos. 269 TR
  • Lift Stations: 13 Nos., capacity of 8-12 m depth
  • Steam Calorifiers: 10 nos., 1600-5400 L
  • Heat Exchanges: 11 nos., 1675 kW & 1805 kW
  • Condensate Recovery Unit: 2 nos., 200 L each