P&C of Sea Water Cooling Supply Piping for Royal Commission at Ras Al-Khair

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Ras Al Khair, KSA
End User Royal Commission for Jubail and Yanbu
Client Royal Commission for Jubail and Yanbu
Project Management
Consultant Bechtel
Type of Project Pipeline
Total Value (SAR) 30.19 Million Saudi Riyal
Start Date May, 2020 (Notice to Proceed)
Finish Date May, 2021
Total Land Area
Total Built-up Area

Work Description

Infrastructure Pipeline

Scope of Work

  • Installation and Testing & Commissioning of 6,000 LM pf 1600 mm dia pipe

Design, Construction and Fit-Out of the DGDA Site Offices

Project Description

Contractor FEMCO & SASEL CONSORTIUM
Location Riyadh, KSA
End User Diriyah Gate Development Authority (DGDA)
Client Diriyah Gate Development Authority (DGDA)
Project Management Faithful+Gould
Consultant Khatib & Alami
Type of Project Office Building
Total Value (SAR) 89 Million Saudi Riyal
Start Date Jul, 2019
Finish Date Jun, 2020
Total Land Area 45,000 m2
Total Built-up Area 12,000 m2

Work Description

Infrastructure and Electrical & Mechanical Works

Scope of Work

  • 45,000 m2 Asphalt and 37,000 m2 Parking Area
  • Underground Storm, Sewage, Potable, Irrigation and Fire Water Network
  • Construction of 2-floors Total 12,000 m2 Steel Structure Office Building
  • Construction and Furnishing of 1 No. Main Guard House
  • Supply and Assembly of All Office Furnitures
  • All associated Civil, Architectural and Electro-Mechanical Works

KFU Projects for Parking Lots for Female Employees and Students

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Al Ahsa, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant
Type of Project Parking & Landscaping
Total Value (SAR) 5.25 Million Saudi Riyal
Start Date Sep, 2018
Finish Date Jan, 2020
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical & Electrical Infrastructure Works

Scope of Work

  • King Faisal University for parking lots for female employees and students.
  • 31000 M2 Area excavation, backfilling, base-coarse and asphalt.
  • All parking area marking, lighting and water drainage system.
  • Parking Gate building all civil, electrical and mechanical work.

Infrastructure for the Preparatory Year in Faysaliyah

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Jeddah, KSA
End User Ministry of Higher Education
Client King Abdulaziz University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 63.8 Million Saudi Riyal
Start Date Nov, 2017
Finish Date May, 2020
Total Land Area
Total Built-up Area

Work Description

Civil, Electrical & Mechanical works

Scope of Work

Work Summary: Infrastructure work for the existing and new building in Al Faysaliyah King Abdulaziz University Campus, work including all civil works and complete electro-mecanical work for chiller plant with mechanical and electrical net works as bellow:

  • Water Cooled Centrifugal Chillers: 11 nos. Capacity 560 TR each (TOTAL 6,160 TR)
  • Chilled Water Primary Pumps: 7 nos. TDH 3 bar, Capacity 2,300 GPM
  • Chilled Water Secondary Pumps: 7 nos. TDH 5 bar, Capacity 1,900 GPM
  • Expansion Tanks: 4 nos. Capacity 900 Gallon
  • Heat Exchangers: 11 nos. 1,750 kW
  • Aboveground and Underground Chilled Water Piping: 3,500 m
  • Sewage Piping System: 2,500 m
  • Potable and Fire Water Piping System: 2,500 m
  • Fire Pumps: 2 nos. TDH 6 bar, Capacity 317 GPM
  • Fire Pump: 1 nos. TDH 8 bar, Capacity 1,000 GPM
  • MV Switchgears: 4 nos. 13.8 kV
  • Transformers: 2 nos. 13.8 / 0.4 kV
  • Emergency Generator: 6 nos. 800 kVA

District Cooling For Community Area Package 1 – Pipeline Distribution Network

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Yanbu, KSA
End User Royal Commission for Jubail and Yanbu
Client Royal Commission for Jubail and Yanbu
Project Management
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 43.98 Million Saudi Riyal
Start Date Oct, 2017
Finish Date Jan, 2021
Total Land Area
Total Built-up Area

Work Description

Civil, Electrical & Mechanical works

Scope of Work

  • Engineering, procurement and construction (EPC).
  • Chilled Water Piping System including valve chambers: 6,000 m.
  • Fibber Optic Cable: 1,500 m.
  • Excavation and Backfilling..

Completion of Fencing Works from Gate No. (2) to Electrical Substation

Project Description

Contractor FEMCO & Sasel Saudi Consortium
Location Al Ahsa, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant Zuhair Fayez Partnership (ZFP)
Type of Project District Cooling & Infrastructure
Total Value (SAR) 8.52 Million Saudi Riyal
Start Date Sep, 2014
Finish Date Mar, 2015
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure Works

Scope of Work

  • Removing and installation of fence around the university with approximately 900 mt. length and excavation 1000 m3 including all lighting works, CCTV and fire alarm.
  • Removing and installation of gate of university including all civil, electrical and mechanical works

Underpass Construction – Dammam University Infrastructure – Phase 3

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client Dammam University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 215 Million Saudi Riyal
Start Date Aug, 2014
Finish Date Sep, 2016
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure Works

Scope of Work

  • Excavation & Backfilling: 115,000 m³ & 52,000 m³
  • Total length: 952 m
  • Width: 30 m
  • Second Pile Shoring System
  • Tensile Piles Under Raft
  • Concrete and Road Works

Project of Supplementation of Infrastructure for the University City Third Phase (Lift Station)

Project Description

MEP Contractor FEMCO & Sasel Saudi Consortium
Location Dammam, KSA
End User Ministry of Higher Education
Client University of Dammam
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 19.52 Million Saudi Riyal
Start Date Aug, 2014
Finish Date Mar, 2016
Total Land Area
Total Built-up Area

Work Description

Civil, Electrical, Mechanical and Instrument works.

Scope of Work

  • Gravity Pipeline; Catch Basins for GRP. GRP pipes 400, 600, 700, 800, 900, 1000, 1200mm dia. GRP manholes having 1200, 1500mm dia.
  • Lift Station; Excavation support secant piles.Total 1612m2 wall to be constructed.Tension piles underneath the lift station.Ductile Iron Pipe and fittings to be supplied and installation. Submergible pumps with motor and control panel, vapor barrier membrane, Compartment System waterproofing, ceiling mounted weather proof fluorescent lighting fixture, grounding, MV cables.
  • Force Main Pipeline; Supply and laying and install GRP pipe with Air Release Valve.
  • Electrical Room construction for Generator; Construction of Electrical room for Generator and Package substation, Supply and install the Package Substation and one unit of the Generator with storage fuel tank, Underground FRP fuel, Auto Transfer switch, grounding, MCC and ICP.

Branch Gate No. 3 – Supplementation of Infrastructure – Phase 3

Project Description

Contractor FEMCO & YUKSEL Consortium
Location Dammam, KSA
End User Ministry of Higher Education
Client University of Dammam
Project Management University PM
Consultant
Type of Project Building
Total Value (SAR) 15.69 Million Saudi Riyal
Start Date Marc, 2014
Finish Date Aug, 2015
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical & Electrical Works

Scope of Work

The purpose of this Contract is execution of infrastructure works for branch gate no. 3. with all electrical and mechanical works and supply and testing of the security system all around the boundary wall and connecting to the main gate.

Replacement Works for King Abdulaziz University Female 200

Project Description

MEP Contractor FEMCO & YUKSEL Consortium
Location Jeddah, KSA
End User Ministry of Higher Education
Client King Abdulaziz University
Project Management University PM
Consultant Fluor Consultants
Type of Project District Cooling & Infrastructure
Total Value (SAR) 69.42 Million Saudi Riyal
Start Date Feb, 2014
Finish Date Nov, 2015
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical & Electrical Replacement Works

Scope of Work

  • Handicapping & Landscaping work.
  • Parking area.
  • Asphalt work; 39,000 m².
  • External lighting.
  • Chilled water piping work (6″ to 20“) – 3560 mt.
  • Potable water piping work (50mm to 200mm Dia) – 2365 mt.
  • Sewage water piping work (110mm to 500mm Dia) – 3445 mt.
  • Irrigation system (20mm to 110mm Dia) – 3550 mt.
  • MV cable 400mm² – 14,400 mt.
  • LV cable system.
  • Cable duct bank for MV & LV
  • Compact substation 400 V – 1500 kVA (2 nos) and 1000 kVA (14 nos).
  • Generator 875 kVA (4nos) and 1500 kVA (2nos).
  • Telecommunication system.