Infrastructure in Girls Colleges in Al Rayyan Complex in Dammam

Project Description

MEP Contractor FEMCO & YUKSEL Consortium
Location Dammam, KSA
End User Ministry of Higher Education
Client University of Dammam
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 349.92 Million Saudi Riyal
Start Date June, 2013
Finish Date Apr, 2017
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical & Electrical Infrastructure Works, Project is divided to two stages, Package 1 & 2.

Scope of Work

  • Excavation & Backfilling: 115,000 m³ & 52,000 m³
  • Service Tunnel: 5,500 m
  • Chilled Water Piping System: 11,000 m
  • Storm Water Piping System: 4,500 m
  • Sewage Water Piping System: 4,000 m
  • Potable Water Piping System: 9,000 m
  • Domestic Water Piping System: 9,000 m
  • Irrigation Water Piping System: 66,000 m
  • Fire Water Piping System: 10,500 m
  • Data, Voice, CCTV, Public Address, Fire Alarm Networks: 4,200m x 5 = 21,000 m
  • MV Distribution Network: 29,000 m
  • LV Distribution Network: 19,000 m
  • Water Storage Tanks
  • Fire & Domestic Water Tank: 1 no. Capacity 5,304 m³
  • Potable Water Tank: 1 no. Capacity 2,673 m³
  • Irrigation Water Tank: 1 no. Capacity 2,460 m³
  • Raw Water Tank: 1 no. Capacity 550 m³
  • Pump Rooms
  • Domestic Water Pump Room: 3 nos. TDH 6.5 bar, Capacity 555 GPM
  • Fire Water Pump Room: 2 nos. TDH 13 bar, Capacity 1250 GPM
  • Irrigation Water Pump Room: 1 no. TDH 7 bar, Capacity 397 GPM
  • Potable Water Pump Room: 3 nos. TDH 7.5 bar, Capacity 365 GPM
  • Chiller Plant
  • Water Cooled Centrifugal Chiller: 6 nos. Capacity 2,946 TR each (TOTAL 17,676 TR)
  • Closed Circuit Cooling Towers: 5 nos.
  • Chilled & Condenser Water Pumps
  • MV Switchgears
  • Transformers
  • Motor Control Centres

Boundary Walls & Gates of the University

Project Description

Contractor FEMCO & YUKSEL Consortium
Location Dammam, KSA
End User Ministry of Higher Education
Client University of Dammam
Project Management University PM
Consultant
Type of Project Building
Total Value (SAR) 33.71 Million Saudi Riyal
Start Date Nov, 2012
Finish Date Jun, 2014
Total Land Area
Total Built-up Area

Work Description

Civil, Structural, Architectural and Electro-Mechanical Works

Scope of Work

  • UOD Hospital area main gate building & 8 km boundary wall with four secondary access gates.
  • Civil works such as concrete pilling, concrete structure, precast, boundary wall, providing gate barriers and all finishing
  • Electrical works such as lighting, power distribution, MV equipment’s, fire alarm,
  • Boundary wall lighting and security CCTV network, telephone & data works
  • Mechanical works such as utility connection to network for potable, seweage & fire water.
  • Package air conditioning & HVAC distribution ducts, storm water network and building plumbing works.

Connection of Buildings of College of Education & Sciences with Girls College in Dammam

Project Description

Contractor FEMCO & YUKSEL Consortium
Location Dammam, KSA
End User Ministry of Higher Education
Client University of Dammam
Project Management University PM
Consultant
Type of Project Building
Total Value (SAR) 33.66 Million Saudi Riyal
Start Date Aug, 2010
Finish Date Mar, 2012
Total Land Area
Total Built-up Area

Work Description

Civil, Architectural and Electro-Mechanical Works

Scope of Work

  • Installation 5000 m22 space frame, and 5000 m2 cover of the steel (sandwich panels)
  • Aluminum works cladding 850 m2, windows and sliding doors
  • Civil works (retaining wall and foundations aand column’s), cement board 2300 m2 granite 2100 m2, interlock 1500 m2.
  • Supply and installaion of 6 pcs Compacted Air Conditioning Units, 19 tone per unit
  • Spiral round duct single wall inside insulation with the feeding opening and the calibration damper
  • Electrical works compact sub-station 1000Kva for transferring from 13.8Kv to 380V 60Hrtz,
  • MDP, DP, Lighting panel and fire alaram system.

Research Centers Project – University City – Dammam

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client University of Dammam
Project Management
Consultant
Type of Project Building
Total Value (SAR) 21.89 Million Saudi Riyal
Start Date Jun, 2010
Finish Date May, 2012
Total Land Area
Total Built-up Area

Work Description

Civil, Structural and Electro-Mechanical Works

Scope of Work

  • Building of the new campus main gate with 3 secondary gates with all electrical and mechanical works and supply and testing of the security system all around the boundary wall and connecting to the main gate.

Infrastructure for Housing of the University City in Dammam – Phase 2

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client University of Dammam
Project Management
Consultant
Type of Project Building
Total Value (SAR) 21.89 Million Saudi Riyal
Start Date Jun, 2010
Finish Date May, 2012
Total Land Area
Total Built-up Area

Work Description

Civil, Structural and Electro-Mechanical Works

Scope of Work

  • Building of the new campus main gate with 3 secondary gates with all electrical and mechanical works and supply and testing of the security system all around the boundary wall and connecting to the main gate.

Infrastructure for KFU Teaching Hospital Project in Al-Ahsa, Phase-1

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Al Ahsa, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant Zuhair Fayez Partnership (ZFP)
Type of Project District Cooling & Infrastructure
Total Value (SAR) 290.8 Million Saudi Riyal
Start Date Jun, 2010
Finish Date Jun, 2013
Total Land Area 500,000 m2
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure & Utilities Works

Scope of Work

Site Development

    • Excavation & Backfilling: 263,000 m³ & 220,000 m³
    • Concrete Works: 8,000 m³
    • Asphalt Works: 52,000 m²
    • Curbstone: 10,000 m²
    • Chilled Water Piping System:           4,500 m
    • Storm Water Piping System: 800 m
    • Sewage Water Piping System: 2,200 m
    • Potable Water Piping System: 2,200 m
    • Raw Water Piping System: 2,800 m
    • Well Water Piping System: 500 m for 3 nos. deep well
    • Reverse Osmosis (RO) Unit: 2 nos. Capacity 750 m³/day
    • Break Water Tank: 1 nos. Capacity 500 m³

Chiller Plant

    • Water Cooled Centrifugal Chillers: 6 nos. Capacity 2,151 TR each (TOTAL 12,906 TR)
    • Air Cooler Radiators: 44 nos. Capacity 269 TR each (TOTAL 11,836 TR)
    • Primary Chilled Pumps: 8 nos. TDH 2.6 bar, Capacity 3,250 GPM
    • Condenser Water Pumps: 8 nos. TDH 3.7 bar, Capacity 7,300 GPM
    • Secondary Chilled Pumps: 5 nos. TDH 6 bar, Capacity 5,700 GPM
    • Boilers: 4 nos. Capacity 7,710 kg/hr

Generator Plant

    • Generators: 5 nos. Capacity 2500kVA each
    • MV Switchgear: 1 no. 13.8 kV, 2500 kVA

Pump Rooms

    • Raw Water Pump: 4 nos. TDH 9.5 bar, Capacity 161 GPM
    • Irrigation Water Pump: 3 nos. TDH 6.5 bar, Capacity 250 GPM
    • Fire Pump: 2 nos. TDH 13.5 bar, Capacity 47 GPM

Connection Between Colleges and Administration in the University City in Dammam, Phase 2

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 8.58 Million Saudi Riyal
Start Date Oct, 2009
Finish Date Jun, 2010
Total Land Area
Total Built-up Area

Work Description

Electro-Mechanical Works

Scope of Work

  • Supply and installation of TV and media.
  • Networks include all cabling network and LCD’s,
  • LED’s for the medical center building.
  • Supply and installation of huge Sculpture DNA clock in the middle of the main hall at Medical Center

Education College Buildings in Dammam – Phase 2 – First Part

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 9.5 Million Saudi Riyal
Start Date Aug, 2009
Finish Date Sep, 2009
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure Works

Scope of Work

  • Including the infrastructure, backfilling,
  • Curbstone, sub-base, base coarse, asphalting,
  • Interlock works of approximate 70,000 m2 road and parking.
  • Building a closed corridor with guard houses between faculty 4.6 m x 400 m.
  • All electrical work, external lighting and internal lighting and plumbing system, sewage network.

Connection Between Colleges and Administration in the University City in Dammam – Phase 1

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 10.67 Million Saudi Riyal
Start Date Mar, 2009
Finish Date Nov, 2009
Total Land Area
Total Built-up Area

Work Description

Electro-Mechanical & Hardscaping Works

Scope of Work

  • Include ducting work, fire alarm and sprinkler system,
  • Granite pavement,
  • Cladding and all electrical work,
  • Data and telephone & internet network system

for the main hall and the connection between colleges and administration building.

Preparation of Infrastructure for the University City in Dammam Second Phase (King Faisal University Permanent campus in Dammam)

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 212.84 Million Saudi Riyal
Start Date Jun, 2007
Finish Date Nov, 2009
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure Works

Scope of Work

  • Site Cleaning with Excavation / Filling of 1,230,000 cu.mtr. of Soil.
  • Construction of Roads with 590 Poles of Street Lights, Walkways, & Parking.
  • Installation of Sewer &p; Irrigation Piping, and 34 KM of Water Distribution Network.
  • Setting up of Sewage Treatment Plant of 1,600 cu.mtr. / day capacity and Sewage Pump Lifting station of 50 LPS. capacity.
  • Also Storm Water Pump Station of 250 LPS capacity is constructed.
  • Installation of 4 nos. Chiller Plants of 1,300 Tons capacity and
  • 3 nos. Cooling Towers of 3,900 GPM capacity,
  • Laying of 1.4 KM of Hydronic Pipes, together with Chilled & Condenser Water pumps.
  • Installation of R.O Plant of 400 cu. mtr per day capacity.
  • Facilities like: Telephone & Computer Data System, Clock System,
  • MATV, CCTV Surveillance, CCMS / BMS / Fire Alarm System,
  • Sprinklers, FM 200 Fire Suppression System & Fire Hydrants, are included.
  • Electrical Works include: Installation of 16 KM of U / G conduits for Elect.
  • Cabling.
  • 4 nos. of 1,500 KVA Generators for Emergency Power,
  • 4 nos. Power Transformers, 1 no. MV Switchgear and
  • Installation of 28 KM of 15 KV MV Cables, 2 nos. LV Switchgear,
  • MCCs, Power & Lighting Panels, Lighting Transformers.
  • 10 KM of LV Cables, Control Boards, and Photo-electric Switches for Street Lights.
  • Grounding, Bonding, and Lightning Protection System