Interior Fit‐Out and Furnishing of Currie & Brown Office, Riyadh

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Riyadh, KSA
End User Currie & Brown
Client Currie & Brown
Project Management IDS Development Management and Consultancy
Consultant IDS Development Management and Consultancy
Type of Project Office Building
Total Value (SAR) 0.75 Million Saudi Riyal
Start Date Jan, 2020
Finish Date Oct, 2020
Total Land Area
Total Built-up Area 650 m2

Work Description

Interior Design and Electrical & Mechanical Works

Scope of Work

  • Supply and Construction of Glass Partitions
  • Supply and Construction of Gypsum Wall Partitions & Ceiling Works
  • Rehabilitation and Improvement of HVAC System
  • Rehabilitation and Improvement of Fire Sprinkler & Fire Alarm System
  • Rehabilitation and Improvement of IP Data System
  • Rehabilitation and Improvement of CCTV System
  • Rehabilitation and Improvement of Access Control System
  • Rehabilitation and Improvement of Power Distribution System
  • Supply and Assembly of All Office Furnitures

Design, Construction and Fit-Out of the DGDA Site Offices

Project Description

Contractor FEMCO & SASEL CONSORTIUM
Location Riyadh, KSA
End User Diriyah Gate Development Authority (DGDA)
Client Diriyah Gate Development Authority (DGDA)
Project Management Faithful+Gould
Consultant Khatib & Alami
Type of Project Office Building
Total Value (SAR) 89 Million Saudi Riyal
Start Date Jul, 2019
Finish Date Jun, 2020
Total Land Area 45,000 m2
Total Built-up Area 12,000 m2

Work Description

Infrastructure and Electrical & Mechanical Works

Scope of Work

  • 45,000 m2 Asphalt and 37,000 m2 Parking Area
  • Underground Storm, Sewage, Potable, Irrigation and Fire Water Network
  • Construction of 2-floors Total 12,000 m2 Steel Structure Office Building
  • Construction and Furnishing of 1 No. Main Guard House
  • Supply and Assembly of All Office Furnitures
  • All associated Civil, Architectural and Electro-Mechanical Works

Infrastructure for the Preparatory Year in Faysaliyah

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Jeddah, KSA
End User Ministry of Higher Education
Client King Abdulaziz University
Project Management University PM
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 63.8 Million Saudi Riyal
Start Date Nov, 2017
Finish Date May, 2020
Total Land Area
Total Built-up Area

Work Description

Civil, Electrical & Mechanical works

Scope of Work

Work Summary: Infrastructure work for the existing and new building in Al Faysaliyah King Abdulaziz University Campus, work including all civil works and complete electro-mecanical work for chiller plant with mechanical and electrical net works as bellow:

  • Water Cooled Centrifugal Chillers: 11 nos. Capacity 560 TR each (TOTAL 6,160 TR)
  • Chilled Water Primary Pumps: 7 nos. TDH 3 bar, Capacity 2,300 GPM
  • Chilled Water Secondary Pumps: 7 nos. TDH 5 bar, Capacity 1,900 GPM
  • Expansion Tanks: 4 nos. Capacity 900 Gallon
  • Heat Exchangers: 11 nos. 1,750 kW
  • Aboveground and Underground Chilled Water Piping: 3,500 m
  • Sewage Piping System: 2,500 m
  • Potable and Fire Water Piping System: 2,500 m
  • Fire Pumps: 2 nos. TDH 6 bar, Capacity 317 GPM
  • Fire Pump: 1 nos. TDH 8 bar, Capacity 1,000 GPM
  • MV Switchgears: 4 nos. 13.8 kV
  • Transformers: 2 nos. 13.8 / 0.4 kV
  • Emergency Generator: 6 nos. 800 kVA

Design, Supply and Construction Of The Pump Station and The Pipe Connecting the Pump Station To the Existing Pipe Strip Tied – In to RQWTS Operating Tank

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Buraidah, KSA
End User Power and Water Utility Co. for Jubail and Yanbu (Marafiq)
Client Power and Water Utility Co. for Jubail and Yanbu (Marafiq)
Project Management
Consultant
Type of Project Water & Power
Total Value (SAR) 6.76 Million Saudi Riyal
Start Date Sep, 2014
Finish Date Mar, 2015
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical, Electrical and Instrument Work

Scope of Work

Pump House

    • Design, Prepare and Excute the Construction Of Pump House Building about 18.6 mts (L) X 13.62 mts(W) X 10.5 mts(H)
    • Construction of LV Switchgear Room in side Pump House Building about 18.6 mts (L) X 13.62 mts(W) X 10.5 mts(H)
    • Supply and Installation of 2.5 Tons Electric Overhead Crane
    • Supply & Installation of 3 nos of Pump w / Motor; Flow rate: 1000m³/h, Head: 40 mts (4 bar)
    • Supply and Installation of Carbon Steel Pipes, Fittings & Flanges for Suction & Discharge Side of Pumps
    • Supply and Installation of Valves for Suction & Discharge Side of Pumps

Valve Chamber

    • Design, Prepare and Excute the Construction Of Flow Control By-Pass Valve Chamber about 8.1 mts (L) X 4.6 mts(W) X 3.85 mts(H)
    • Supply and Installation of Flow Control, Butterfly Valve and Carbon Steel Pipes & Fittings for Valve Chamber

Branch Gate No. 3 – Supplementation of Infrastructure – Phase 3

Project Description

Contractor FEMCO & YUKSEL Consortium
Location Dammam, KSA
End User Ministry of Higher Education
Client University of Dammam
Project Management University PM
Consultant
Type of Project Building
Total Value (SAR) 15.69 Million Saudi Riyal
Start Date Marc, 2014
Finish Date Aug, 2015
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical & Electrical Works

Scope of Work

The purpose of this Contract is execution of infrastructure works for branch gate no. 3. with all electrical and mechanical works and supply and testing of the security system all around the boundary wall and connecting to the main gate.

Replacement and Development of Infrastructure for King Khalid Hospital

Project Description

Contractor FEMCO & YUKSEL Consortium
Location Al Kharj, KSA
End User Ministry of Health
Client King Khalid Hospital
Project Management Hospital PM
Consultant Specialist Group for Engineering Consultancy
Type of Project Building Renovation
Total Value (SAR) 97.75 Million Saudi Riyal
Start Date Feb, 2014
Finish Date Sep, 2019
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical & Electrical Replacement Works

Scope of Work

The purpose of this Contract is execution of renovation works such as but not limited to: mechanical works, electrical works, landscaping works, parking lots works. cables, communication system and information technology, internal/external lighting, package substations (transformation station and distribution station), generators, drinking water distribution system, HVAC system, lighting, finishing works, wood works, roads and parking lots organization.

Replacement and Development of Infrastructure for Qatif Central Hospital

Project Description

Contractor FEMCO & YUKSEL Consortium
Location Qatif, KSA
End User Ministry of Health
Client Qatif Central Hospital
Project Management Hospital PM
Consultant Specialist Group for Engineering Consultancy
Type of Project Building Renovation
Total Value (SAR) 66.72 Million Saudi Riyal
Start Date Feb, 2014
Finish Date Sep, 2017
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical & Electrical Replacement Works

Scope of Work

The purpose of this Contract is execution of renovation works such as but not limited to: mechanical works, electrical works, landscaping works, parking lots works. cables, communication system and information technology, internal/external lighting, package substations (transformation station and distribution station), generators, drinking water distribution system, HVAC system, lighting, finishing works, wood works, roads and parking lots organization.

Replacement and Development of Infrastructure for Jubail General Hospital

Project Description

Contractor FEMCO & YUKSEL Consortium
Location Jubail, KSA
End User Ministry of Health
Client Jubail General Hospital
Project Management Hospital PM
Consultant Specialist Group for Engineering Consultancy
Type of Project Building Renovation
Total Value (SAR) 71.99 Million Saudi Riyal
Start Date Feb, 2014
Finish Date Sep, 2017
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical & Electrical Replacement Works

Scope of Work

The purpose of this Contract is execution of renovation works such as but not limited to: mechanical works, electrical works, landscaping works, parking lots works. cables, communication system and information technology, internal/external lighting, package substations (transformation station and distribution station), generators, drinking water distribution system, HVAC system, lighting, finishing works, wood works, roads and parking lots organization.

P&C for Sea Water Pump Station (201-C01)

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Ras Al Khair, KSA
End User Royal Commission for Jubail and Yanbu
Client Royal Commission for Jubail and Yanbu
Project Management Bechtel
Consultant Bechtel
Type of Project Water & Power
Total Value (SAR) 429.33 Million Saudi Riyal
Start Date Dec, 2013
Finish Date Jul, 2017
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical & Electrical Infrastructure Works. The pumping station shall pump 75.000 m3 / hr sea water to the system network for Ras Al Khair Industrial City when completed.

Scope of Work

Sea Water Cooling Pump Station

  • Vertical Mixed Flow Pump: 4 nos. Capacity 15,000 m³/hr. each (TOTAL 60,000 m³/hr.).
  • Mechanical Bar Screen: 4 nos. Capacity 15,000 m³/hr. Clearing Space between bars 80 mm.
  • Travelling Band Screen: 4 nos. Capacity 15,000 m³/hr. Screening Aperture Size 5×5 mm.
  • FRP/GRP Water Piping including Valves and Fittings: 1,780 m up to 3,300 mm dia.
  • Overhead Crane: 1 no. Lifting Capacity 40 ton.
  • Excavation and Backfilling: 45,000 m³ and 5,000 m³.
  • Concrete: 18,000 m³.

HYPOCHLORITE Generation Building

  • Sodium Hypochlorite Generators: 3 nos. Capacity 540 kVA.
  • Seawater flow through one Generator: 50 m³/hr.
  • Hypochlorite Production: 100 kg/h.
  • Hypochlorite Concentration: 2,000 ppm.
  • Seawater Booster Pump: 2 nos. TDH 1.8 bar Capacity 528 GPM.
  • Automatic Self-Cleaning Filters: 2 nos. Capacity 528 GPM.
  • Sodium Hypochlorite Storage FRP Tank: 2 nos. Capacity 80 m³.
  • SEC 115 kV Power Supply: Including design & engineering works of 115kV cabling system.

Site Development

  • Intake Dredging Works: 200,000 m³ Dredging of intake canal.
  • Shoreline Rip Rap Protection: 9,300 m².
  • Shoreline Interlocking: 1,800 m².
  • Toe-Down to Dredged Channel: 600 m³.
  • Grading: 200,000 m².
  • Surfacing: 5,000 m².
  • Asphalt: 12,000 m²
  • Jelly Fish Basin: Length 100 m, Width 60 m and Depth 2 m.
  • Cofferdam Temporary Works: 60 x 100 m.
  • Staff Control Building
  • Switchgear Building
  • Workshop Building
  • Guard House
  • SEC Building.

Replacement and Development of Infrastructure for King Fahad Hospital

Project Description

Contractor FEMCO & YUKSEL Consortium
Location Al Ahsa, KSA
End User Ministry of Health
Client King Fahad Hospital
Project Management Hospital PM
Consultant Specialist Group for Engineering Consultancy
Type of Project Building Renovation
Total Value (SAR) 175.2 Million Saudi Riyal
Start Date Dec, 2013
Finish Date Jun, 2019
Total Land Area
Total Built-up Area 45,000 m2

Work Description

Civil, Mechanical & Electrical Replacement Works

Scope of Work

The purpose of this Contract is execution of renovation works such as but not limited to: mechanical works, electrical works, landscaping works, parking lots works. cables, communication system and information technology, internal/external lighting, package substations (transformation station and distribution station), generators, drinking water distribution system, HVAC system, lighting, finishing works, wood works, roads and parking lots organization.