Project Description
Contractor | FEMCO & YUKSEL Consortium |
Location | Al Ahsa, KSA |
End User | Ministry of Health |
Client | King Fahad Hospital |
Project Management | Hospital PM |
Consultant | Specialist Group for Engineering Consultancy |
Type of Project | Building Renovation |
Total Value (SAR) | 175.2 Million Saudi Riyal |
Start Date | Dec, 2013 |
Finish Date | Jun, 2019 |
Total Land Area | |
Total Built-up Area | 45,000 m2 |
Work Description
Civil, Mechanical & Electrical Replacement Works
Scope of Work
The purpose of this Contract is execution of renovation works such as but not limited to: mechanical works, electrical works, landscaping works, parking lots works. cables, communication system and information technology, internal/external lighting, package substations (transformation station and distribution station), generators, drinking water distribution system, HVAC system, lighting, finishing works, wood works, roads and parking lots organization.