  • Project Name: WETICO - Jeddah SWRO III Project (240 Million Liters Per Day)
  • Location: Jeddah / K.S.A.
  • Contractor: WETICO (Subcontractor: Faisal Electro-Mechanical Co. Ltd.)
  • Client: WETICO
  • Type of Project: Water & Power
  • Value (SR): 30.17 Millions
  • Start Date: Aug. 2011
  • Finish Date: Sep. 2013
  • The Scope of Work:
    • RO Trains 1st & 2nd Pass, 254 SMO & 316 L stainless pipes fabrication and erection works
    • RO Trains rack installation
    • Pressure Vassals (4,464 nos.) & Membrane (13,168 nos.) installation works.
    • HP high pressure pump installation.
    • Static mixer, valves, flow metersetc. installation.
    • Flushing and product pumps installation.
    • CIP system, Carrier water system and Calcium Hypoclorite system pumps & erection works.
    • Utilities piping works
    • Electrical & Instrumentation Control system erection works.
    • Grouting works for electro-mechanical activities