  • Project Name: Tank Farm Piping for MSF & RO Plants
  • Location: Jubail / K.S.A.
  • Contractor: Consortium: Faisal Electro-Mechanical Co. Ltd. – Yuksel Insaat Saudia Co. Ltd.
  • Client: Saline Water Conversion Corporation (SWCC)
  • Type of Project: Water & Power
  • Value (SR): 3.5 Millions
  • Start Date: Jul. 2003
  • Finish Date: Jul. 2004
  • Work Description:
    Piping Works
  • The Scope of Work:
    • Dismantling & Removal of dia. 32" Temporary Link Line, and dia 36" Temporary Suction Line, and dia. 36"
      Temporary By-Pass Line, together with Butterfly Valves and Drain & Vent Valves.
    • Supply and Installation of Piping in the Pump House of Blending Station – BS 1.
    • Supply, Laying & Embedding of new Link Line ( for MSF 1 ) of dia. 32", 36", & Branch - off Line dia. 48" together
      with Valves.
    • Supply & Installation of Power Supply & Control Equipment for new monitoring equipment of Phase 1 Line of dia. 36"
      ( Flow meters, Hardness Analyzer, pH analyzer )
    • Supply & Installation of 3 nos. Valve Chambers, Cable Duct banks, and Manholes for Elect. System.
    • Civil Works for Yard Shaft & Cable Pulling Shafts.