  • Project Name: Project of Infrastructure for the Preparatory Year in Faysaliyah
  • Location: Jeddah / K.S.A.
  • Contractor: Faisal Electro-Mechanical Co. Ltd.
  • Client: King Abdulaziz University
  • Type of Project: District Cooling & Infrastructure
  • Value (SR): 63.8 Millions
  • Start Date: Nov. 2017
  • Finish Date: Mar. 2019
  • Work Description:
    • Civil, Electrical & Mechanical Work
  • The Scope of Work
      • • Work Summary : infrastructure work for the existing and new building in Al faysalieh King Abdul Aziz campus, work including all civil works and complete electromecanical work for chiller plant with mechanical and electrical net works as bellow :
      • • Construction of the Chiller plant Building & Pumps Building
      • • Supply and Installation; Chiller (560 tone/each) (11 no), Primary and secondary pumps (7 no each), heat exchanger (12 no), Above and under ground child water pipes with required valve chambers, Pipes for potable and fire fighting networks with required valve chambers, Pipes and manholes for sewage system, medium voltage cables netwaork, Low voltage cables net work, Medium voltage switch gear (4 no), Oil type transformer (8 no), Main distribution panels for chillers (11 no), Ring main unit (21 no), MCC panels, Generators (6 no), Automatic transfer switch (ATS) (6 no), Fuel tanks, Building management system (BMS) for the complete system.
      • • Testing and Conissioning for the complete system.