  • Project Name: Preparation of Infrastructure for the University City in Dammam Phase 4 & 6, Utility Works. (King Faisal University Permanent Campus in Dammam)
  • Location: Dammam / K.S.A.
  • Contractor: Faisal Electro-Mechanical Co. Ltd.
  • Client: King Faisal University
  • Type of Project: District Cooling & Infrastructure
  • Value (SR): 101.39 Millions
  • Start Date: Mar. 2005
  • Finish Date: Nov. 2007
  • Work Description:
    Civil, Mechanical, & Electrical Infrastructure Works
  • The Scope of Work:
    • Excavation & Back-filling of 1,362,694 cu. mtr. of Soil, Construction of 107,700 LM of Flexible Pavements, with 92,200 LM of Curbs & Gutters and 61,000 sq. mtrs. of Sidewalks.
    • 769 LM of Underground Piping (FRP) were laid, and Water Tank of 1,800 cu.mtr. was constructed.
    • R.O Plant of 600 cu.mtr. / day capacity was installed with Water Well and 14.13 KM of Water Network Piping.
    • Sewage Treatment Plant (STP) and Sewage Lift Station is provided with Installation of 5.12 KM of Sanitary Sewage Piping.
    • 5.34 KM of Irrigation Piping has been laid.
    • 50 mtrs. of LPG Pipes ( above ground ) have been installed with 2 nos. of LPG Tanks of 40,000 USG capacity.
    • 2 nos. of Centrifugal Chillers and 2 nos. of Cooling Towers have also been erected.
    • Electrical Works include: Installation of Power & Distribution Transformers, LV Switchgear, and Street Lighting Poles
    • Communication & Data Processing Equipment, Telephone & Inter-com System. Building Automation & Controls and Security Surveillance System were also added.