Completed Projects

« Previous   Next »

  • Project Name: Preparation of Infrastructure for the University City in Dammam Phase 1, Utility Works. (King Faisal University Permanent Campus in Dammam)
  • Location: Dammam / K.S.A.
  • Contractor: Consortium: Faisal Electro-Mechanical Co. Ltd. ÷†Yuksel Insaat Saudia Co. Ltd.
  • Client: King Faisal University
  • Type of Project: District Cooling & Infrastructure
  • Value (SR): 90.98 Millions
  • Start Date: Sept. 2002
  • Finish Date: Aug. 2005
  • Work Description:
    Civil, Mechanical, & Electrical Infrastructure Works
  • The Scope of Work:
    • Development of 77 Hectares area with Excavation / Filling of 774,300 cu.mtr. of soil, preparation of 2.60 KM of Slope Embankment.
    • Construction of Roads with 511 poles of street Lights, Walkways & Parking.
    • Construction of 2.75 KM of Storm Drainage System. Installation of 3.47 KM of Irrigation Piping, and LPG Network of 1.94 KM with Installation of two nos. LPG Tanks with total capacity of 46,000 gallons.
    • Setting-up of R.O. Plant of 600 cu. mtr. per day capacity with Water Well, and with 600 cu. mtr. Underground Water Tank, 600 cu. mtr. Sweet Water Tank and 1800 cu. mtr. Raw Water Tank. Also installed 8.96 KM of Water Distribution Network with pipe sizes ranging from dia.: 25 to 315 mm.
    • Setting-up of Sewage Treatment Plant of 1340 cu .mtr. per day capacity and Installation of 4.62 KM of Sewer Pipelines.
    • Installation of 3 Chiller Plants of 1,300 Tons capacity, 3 nos. Cooling Towers of 3,900 GPM capacity & laying of 6.73 KM of underground Pipes, sizes ranging from 150 to 900 mm. dia. Also, 3 nos. of Chilled & Cond. Water Pumps, 8 nos.of AHUs, & 11 Exhaust Fans were installed. Mech. Works also include packages of Storm Water Pumping Station and Sewer Pumping Station.
    • Construction of 'Utility Building' with facilities like: Telephone & Computer Data System, Clock System, MATV, CCTV surveillance, CCMS / BMS / Fire Alarm System incl. Sprinklers, FM 200 Fire Suppression System & Fire Hydrants.
    • Electrical Works include: Installation of 26 KM of uPVC conduits for Elect. Cabling.
    • Emergency Electric Power Sub-station with 2 nos. of 1,500 KVA Generators, Power Transformers, MV Switchgear of 40 MVA / 13.8 MV capacity and Installation of 38.5 KM of 15 KV MV Cables., LV Switchgear, MCCs, Power & Lighting Panels, Lighting Transformers, 14.7 KM LV Cables, Control Boards, and Photo-electric Switches for Street Lights.
    • Grounding, Bonding, and Lightning Protection System.