Completed Projects

« Previous   Next »

  • Project Name: Preparation of Infrastructure for the University City in Al-Ahsa, Phase-3, Stage-1 (King Faisal University Permanent Campus in Al-Ahsa)
  • Location: Al Ahsa / K.S.A.
  • Contractor: Consortium: Faisal Electro-Mechanical Co. Ltd. – Yuksel Insaat Saudia Co. Ltd.
  • Client: King Faisal University
  • Type of Project: District Cooling & Infrastructure
  • Value (SR): 600.95 Millions
  • Start Date: Aug. 2007
  • Finish Date: Dec. 2011
  • Work Description:
    Civil, Mechanical, & Electrical Infra-Structure Works for Four (4) Sub - Packages as detailed below
  • The Scope of Work:
    • Sub-Package 1: All Electro-Mechanical Works for: Supply & Installation of 7 nos. Chiller Plants of 3,150 Tons
      capacity, 6 nos. Cooling Towers of 9,290 GPM capacity & Pump Station Building with 7 nos. each of Chilled
      Water Pumps of 3,877GPM capacity, and Cooling Water Pumps of 9,290 GPM Discharge Capacity.
    • Sub-Package 2: All Civil & Electro-Mechanical Works for: Supply & Installation of Sewage Treatment Plant (STP), Reverse Osmosis Plant (R.O), and Emergency Generator Building with 2 nos. Stand-by 1,000 KVA capacity Generators, and 2 nos. Diesel Gen-Sets of 1,000 KW capacity, and Utilities of STP & R.O.
    • Sub-Package 3: Supply & Installation of Piping Networks for:
      1. Chilled Water System – 14,790 mtrs.
      2. Sanitary Sewer System – 9,084 mtrs.
      3. Sweet Water - 8,904 mtrs
      4. Raw Water Distribution System – 11,132 mtrs.
      5. Well Water System – 2,021 mtrs.
      6. Effluent Water Distribution System – 3,605 mtrs.
      7. Storm Water Drainage System – 13,288 mtrs.
      8. 8Site Grading & Roads Works
      9. Lift Stations – Elec.-Mech Works for 6 nos. & Civil Works for 5 nos
      10. All Electrical Works: comprising of Supply & Installation of 7,380 mtrs. of 13.8 KV medium voltage and Communication Network Cables, and 16,390 mtrs. of 15 KV Cu. / XLPE Cables.
    • Sub-Package 4: Works related to Landscaping, Hardscaping Works of Pergola & Shade Structures, Stamp Pavement Works, Water Display Networks, Irrigation System, Plantations, Drinking Water Fountains, Tennis Courts, Compact Sub-Stations, and Street Lighting Electrical Works.
    • Site Leveling: 428,000 cu.mtr. of Excavation, 1,028,000 cu. mtr. of Back-filling, 50,000 cu.mtrs. of Concrete Works and 325,000 sq.mtrs. of Asphalt Cover Area.