  • Project Name: Completion of Fencing Works from Gate No. (2) to Electrical Substation
  • Location: Al Hofuf / K.S.A.
  • Contractor: Consortium: Faisal Electro-Mechanical Co. Ltd. – Sasel Saudi L.L.C
  • Client: King Faisal University
  • Type of Project: District Cooling & Infrastructure
  • Value (SR): 8.52 Millions
  • Start Date: Sep. 2014
  • Finish Date: Mar. 2015
  • Work Description:
    Civil, Mechanical, Electrical & Infrastructure works
  • The Scope of Work:
    • Removing and installation of fence around the university with aproximately 900 mt. length and excavation 1000 m3 including all lighting works, cctv and fire alarm.
    • Removing and installation of gate of university including all civil, electrical and mechanical works