  • Project Name: Addition of Chillers for Enhancement of the Air-conditioning in King Khalid Medical City in King Saud University
  • Location: Riyadh / K.S.A.
  • Contractor: Faisal Electro-Mechanical Co. Ltd.
  • Client: King Saud University
  • Type of Project: District Cooling & Infrastructure
  • Value (SR): 21.67 Millions
  • Start Date: Feb. 2012
  • Finish Date: Nov. 2013
  • The Scope of Work:
    HVAC
    • Supply and install nine cooling towers, type closed loop, heat rejection 7,497,000 BTU / Hr. each water flow 1,500 GPM, 60HP fan motor.
    • Supply and install three water cooled Chillers each 1,500 ton of refrigeration and single compressor.
    • Complete installation of piping network for chilled water system with instrumentation, control, expansion join and valves.
    • Supply and install three Chilled water pumps centrifugal constant flow double suction split case type water flow rate 2,000 GPM @ 126ft. TDH, 200 HP motor, including control panel.
    • Supply and install three Condenser pumps centrifugal constant flow double suction split case type water flow rate 4,500 GPM @ 130ft. TDH, 300 HP motor, including control panel.
    • Supply and install one Distribution pump centrifugal constant flow double suction split case type water flow rate 4,400 GPM @ 100ft. TDH, 200 HP motor, including control panel.

    FIRE FIGHTING SYSTEM
    • Supply and install CO2 cylinders system, 180 Kgs capacity including pipes, nozzle outlet, heat detectors for three chills.